Construction equipment and work vehicles grading a new roadway section alongside active traffic lanes as part of the SR 167 Corridor Improvements Project.

SR 167 Corridor Improvements Project, WA

Image Credit: Atkinson Construction

AAR Testing and Inspection, a SOCOTEC Company, provided construction materials testing, special inspections, field quality assurance, and electrical system inspection support for the SR 167 Corridor Improvements Project, helping support the modernization of Washington State's express toll lane infrastructure.

Key Information 

Project Name: SR 167 Corridor Improvements Project

Client: Northup/Harbor Pacific

Owner: Washington State Department of Transportation (WSDOT)

Location: Pierce and King Counties, WA

Project Value: $102 Million

Services Provided: Construction Materials TestingSpecial Inspections and QA/QC Oversight

background dark blue

Talk to our experts

Chris CHRISTENSEN

Division Principal

Redmond, WA

Division Principal

Chris.Christensen@socotec.us +1 425 750 6953

The Challenge 

Modernizing Washington's Express Toll Lane Corridor

The SR 167 Corridor Improvements Project supports the modernization of the Washington State Department of Transportation's (WSDOT) express toll lane system by replacing aging tolling infrastructure with updated electronic tolling technology.

The project aligns the SR 167 toll system with the I-405 Express Toll Lane network, creating a continuous 50-mile express toll corridor extending from SR 512 in Puyallup to the I-405/I-5 interchange in Lynnwood. The improvements are designed to provide a more consistent tolling experience while improving highway operations and travel reliability.

The project included:

  • Installation of 64 drilled shaft foundations supporting 37 sign structures, including 27 sign bridges and 10 cantilevers.
  • Installation of 294 permanent signs, including new electronic toll rate and travel signs.
  • Resurfacing of the southbound Green River Bridge.
  • Lane reconfiguration to expand roadway capacity.

Delivering these improvements required construction activities within an active highway environment while maintaining toll operations and minimizing impacts to ongoing transportation activities.

Additional project challenges included:

  • Nighttime and staged traffic control required to limit lane closures while maintaining corridor mobility.
  • Strict interface requirements between roadway work, electrical systems, and WSDOT’s regional tolling network.
  • Limited workspace constraints near median barriers, shoulders, and access areas.
  • Coordination with multiple stakeholders, including WSDOT’s Toll Division, electrical subcontractors, and ITS vendors.

The SOLUTION

Construction Materials Testing, Special Inspections, and Quality Assurance

AAR Testing and Inspection, a SOCOTEC Company, supported the project by providing construction materials testing, special inspections, field quality assurance, and electrical system inspection services throughout construction.

Working closely with the contractor and WSDOT technical teams, our team helped verify that tolling equipment foundations, electrical installations, communications infrastructure, and structural components met project specifications while construction progressed within an active highway corridor.

Services Provided

  • Concrete foundations and embedments for tolling equipment 
  • Aggregate and base preparation for gantry and sensor supports 
  • Soils and compaction testing at toll equipment locations 

  • Reinforcement and formwork at electrical foundation points 
  • Structural steel and bolting for gantries, cameras, and sensor mounts 
  • Verification of conduit placement, grounding systems, and electrical access pits 
  • Inspection of drainage integration around new electrical infrastructure 

  • Observation of conduit layout verification in toll gantry zones 
  • Inspection coordination with electrical subcontractors for signal and camera systems 
  • Field verification of clearances, access covers, and system embedment prior to backfill 
  • Support for coordination between toll hardware installation and roadway electrical feeds 

  • Daily reporting and communication with WSDOT tolling and design staff 
  • Inspection continuity during phased traffic operations and lane restrictions 
  • Testing, observation and documentation of site restoration around electrical installations 

Construction workers install a concrete drainage structure adjacent to the SR 167 highway as part of the SR 167 Corridor Improvements Project.

The Results 

Supporting Reliable Transportation Infrastructure

The SR 167 Corridor Improvements Project modernized critical tolling infrastructure while supporting a more seamless travel experience across Washington's regional express toll lane network.

Through comprehensive construction materials testing, special inspections, field quality assurance, and electrical inspection support, AAR Testing & Inspection, a SOCOTEC Company, helped support the successful installation of tolling infrastructure within an active highway environment.

The project demonstrates our ability to deliver multidisciplinary inspection and quality assurance services for complex transportation infrastructure projects involving roadway improvements, electrical systems, and intelligent transportation technologies.